The Abu Dhabi International Airport Expansion was one of the largest and most complex infrastructure programs in the Gulf region — a multi-billion dollar, decade-long initiative to dramatically expand the capacity of Abu Dhabi's primary international gateway. PARSONS International served as Program Management Consultant with a team of 150–200 professionals coordinating across dozens of contractors, consultants, and government stakeholders.

Prior to the systems implementation, cost, schedule, contract, and executive reporting was done entirely manually — consuming enormous effort and introducing unacceptable risk of error on a publicly critical program. The mandate was to replace this with a robust, scalable program controls infrastructure that could serve the full 10+ year program lifecycle.

Challenge & Solution
Large infrastructure construction site
⚠ Challenge

Manual reporting on a $10B program

150–200 program professionals compiling monthly executive reports entirely by hand — dozens of hours lost every month on a decade-long, publicly critical aviation program with zero tolerance for data inaccuracies.

Aviation program management
✦ Solution

ARES-PRISM + P6 integration

Full implementation of ARES-PRISM and PRISM G2 for contracts, variations, commitments, and baseline tracking — integrated with Primavera P6 for real-time schedule-cost alignment and automated executive reporting.

$10B+

Program value supported with automated controls

The program controls infrastructure implemented supported the full 10+ year lifecycle of one of the Gulf's most significant aviation megaprograms — delivering 60–80 hours per month of reporting savings from day one.

Solution Delivery
1

ARES-PRISM & PRISM G2 Implementation

Implemented and fully configured ARES-PRISM and PRISM G2 for the complete program controls function — Contracts Management, Variations, commitments tracking, and Primavera P6 integration.

2

Monthly Actuals & Commitment Import Cycle

Configured and managed the monthly cycle of actual cost imports, commitment updates, and baseline estimate tracking — always-current view of cost performance against the approved budget.

3

Primavera P6 Schedule Integration

Maintained the PRISM-P6 integration to keep schedule and cost data aligned — enabling earned value analysis and a unified view of program performance across both dimensions.

4

Executive Reporting Automation

Replaced the manual monthly executive reporting process with system-generated PRISM reports — eliminating 60–80 hours per month of manual data collection and delivering more accurate outputs.

5

Contracts & Variations Management

Configured Contracts and Variations modules to track all contract awards, change events, and variation orders across all contractor interfaces — full visibility of contractual budget impact.

Technology Stack
💼ARES-PRISM📋PRISM G2📅Primavera P6📄Contracts & Variations📊Executive Reporting💰EVM📈Cost Forecasting
Key Outcomes
60–80 hours per month recovered — monthly executive report preparation replaced by automated system-generated outputs.
Full cost & schedule integration — PRISM and P6 integration gave leadership a unified performance view across both dimensions.
Scalable infrastructure for 10+ years — the PRISM implementation supported the full program lifecycle without platform replacement.
Contractual commitment visibility — all contracts, variations, and budget impacts tracked in real time across all contractor interfaces.